| 级 | PI | 工单 | 成品 | 客户 | 箱 | 计划 | 产能 | 台时 | 素球 | 物料 | 交期 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| B | PI226039 | C105-260910001 | SEVEN | 350 | 350 | K10 | 5.8h | 未到 | 923 | 2026-10-15 | |
| B | PI226039 | C105-260910002 | SEVEN | 350 | 350 | K10 | 5.8h | 2026-09-17 | 923 | 2026-10-15 | |
| B | PI226039 | C105-260910003 | SEVEN | 200 | 200 | K10 | 3.3h | 2026-09-15 | 923 | 2026-10-15 | |
| B | PI226039 | C105-260910004 | SEVEN | 200 | 200 | K10.5 | 2.7h | 2026-09-22 | 923 | 2026-10-15 | |
| A | PI226042 | C105-260910005 | MOSES | 63 | 63 | K2.9 | 2.7h | OK | 923 | 2026-10-15 |